CASE STUDIES

Working with WPG on powering temporary site facilities

CLIENT

West Power Group (WPG)

LOCATION

Perth, Western Australia

APS and WPG collaborated on a Perth Metro project, powering site facilities 24/7. Together, they worked to reduce CO₂ emissions and diesel consumption for the office compound.

Like many construction projects, the client faced an increase in staffing requirements over the duration of the project. This presented a challenge: the diesel generators for the site office compound had to be sized for peak demand, corresponding to the periods of maximum staffing and power requirements. Consequently, during the early stages of the project, these generators often operated under light loads. This light loading can lead to engine deglazing and inefficient fuel consumption, resulting in excess diesel usage.

MONTHLY CO2 EMISSIONS REDUCTION (BATTERY & SOLAR)
0 KG
GENERATOR RUN HOURS WITH BATTERY & SOLAR

Foxtheon Battery Energy Storage System

By incorporating a Foxtheon Battery Energy Storage System into their site office compound in conjunction with an existing generator, WPG significantly reduced diesel consumption over the project lifecycle. The battery became the primary power source, while the generator was responsible for recharging. Once installed, the BESS & Generator combination lead to the diesel generator reducing its daily run hours from 24 to 8. A few months after the BESS was installed, a 40kW Solar PV system was installed on site. This reduced the daily run hours from 8 to 3.84hrs per day.

Key Benefits WPG Identified For Their Operations

Reduction in CO2 Emissions: Reduced generator run time led to lower CO2 emissions. Data from the Foxtheon Remote Monitoring system showed monthly reductions of 1,557kg with Battery Only and 3,175kg with Battery & Solar over three months.

Improved Generator Efficiency: Integrating a battery with diesel generators enhances efficiency. It ensures the generator runs at 50-80% capacity while recharging, preventing engine deglazing caused by light loading.

Reduction in Noise Pollution: Cutting generator run time from 24 to 8 hours reduced noise pollution. Though not a major issue at this site, it’s important for projects near living areas.

The integration of a Battery Energy Storage System has not only provided West Power Group with substantial operational benefits, but it has also positioned them as a leader in sustainable construction practices. Through innovation and collaboration with APS, they have demonstrated a commitment to reducing environmental impact while meeting the demands of modern construction projects

READY TO PARTNER WITH APS FOR YOUR POWER PROJECT?

APS offers cutting-edge technology and exceptional quality to elevate your projects. Enhance your productivity and achieve exceptional results. Choose the perfect power partnership and elevate your projects to new heights APS. Get in touch with us today on (08) 9455 2111. 

Ready to empower progress in your next project with APS?

Enquire with our team today on how we can assist you.